Dual Occupancy for Beginners
Beginners guide to dual occupancy subdivision in Melbourne.
Are you a first time developer thinking of developing a property with two homes? You can benefit from the added equity that the subdivision will generate?
The Land
Summary:
If keeping the existing house- make sure you can build a 3 metre wide driveway to the backyard where the second house will sit.
Have enough land in the backyard to provide mandatory open spaces ( think courtyard) in the backyard for both houses. These can range from 25sqm. to 80sqm. per dwelling
Have space for carparking for both houses
The cost of the site should result in acceptable development margins
The Zoning should allow development.
The Schedule to the Zoning should be development friendly.
The Planning overlays (Controls) should not be too restrictive.
The property title should be free of a single dwelling covenant (restriction).
Need these checked by a Registered Planner?
There are a myriad of things to consider when finding a suitable dual occupancy development site.
Some of these are listed below.
-
The site width should allow for two crossovers in the ideal scenario but many Councils in Melbourne are clamping down on this type of duplex developments
-
The vehicle accessway to the backyard should be a minimum 3m in width and compliant to meet the now mandatory safety standards
-
The site length and area should allow adequate north facing open space for recreation and landscaping
-
The site should be close to infrastructure, schools, shops and transport
-
The title should be clear of development restrictions like single dwelling covenant and preferably without any easements
-
All the essential services should be available onsite or in close proximity and run in the most advantageous position
-
The site orientation should be perfect so that the amenities of neighbouring properties are not adversely affected
-
The zoning of your land and it's associated Schedule should not be too restrictive
-
The planning overlays on your land should not be too restrictive
-
The site should be fairly level as sloping blocks may cost more to build. However sites with great views benefit from sloping land
-
There should be little or no significant vegetation on the site and on abutting sites within say 5 m of the common boundaries
-
A soil test should demonstrate the foundations will not require additional strengthening
-
There should be no encroachments on your title boundary or by your property on adjoining allotments
-
There should preferably be precedents for similar development in your neighbourhood
-
There should be no planning overlays burden development
-
Your local Council should encourage development to meet their housing stock forecast
Ready to start your project?
Contact Swarup our Founder for an obligation free, high level opinion of the development potential for your land.
Swarup turned his first home into a successful dual occupancy subdivision.
He experienced stiff opposition from the local Council and neighbours who had heritage mansions with tennis courts and swimming pools. His property even had a listed (Heritage) tree! But his persistence, knowledge and design skills won at the end of the day.
His second project was 3000sqm.of absolute waterfront land no one wanted for three decades due to the difficult land zoning. He turned this "lemon" into a residential zoned land in 2 years.
The Steps for a successful Dual Occupancy in Victoria
These are the Steps to follow:
-
Prepare the dual occupancy home plans for Council
-
Lodge the Plans, elevations, shadow diagrams, Site context, planning report etc to Council
-
After 28 days Council will respond with their feedback
-
Respond to the feedback to Council's satisfaction
-
Council advertises the Application. Neighbours and others can object
-
Council makes a decision
-
Address the Permit conditions to get drawings stamped (endorsed)
-
After drawings are stamped by Council or during this period start construction drawings- architecture, engineering, soil report, thermal assessment at the least
-
Have Construction drawings stamped /certified by Building Surveyor
-
Seek Builder's quotes and start the build
-
If building, apply for subdivision once slab is poured and essential services are connected. You could lodge a preliminary subdivision at Step 2 also.